DIARY OF OPERATIONS
- 04/03/1996 Departure of Italian Team with three members of R/V Gelendzhik surveyor team from Bologna (Italy).
- 05/03/1996 14.00 Arrive at Durban Airport, 15.00 on board of R/V Gelendzhik.
- 06/03/1996 Gravimeter calibration
- 07/03/1996 Bunkering, provisions and gravimeter calibration. 19.00 Departure from Durban for operation area.
- 08-14/03/96 Transit to operation area. Check and control of instrumentation. Hardware and software upgrade of computer center.
- 14/03/1996 17:20 Start of multibeam line 0001. Sound velocity profile calculated from Levitus database. Bad sea state. 19:40 Italian and russian magnetometers on. 22:40 Very bad sea state. Acquisition problems on Italian magnetometers. Probable cable disconnection.
- 15/03/1996 Reached planned point 1 (51 31.8'S, 5 25.18'E). Italian 1st magnetometer recovered. 2nd lost. Repair and start of sigle magnetometer survey (offset 330 m from GPS antenna). Magnetometer, gravimeter and multibeam profiling.
- 16/03/1996 Magnetometer, gravimeter and multibeam profiling. Sound velocity profiles SVP1, SVP2. 19:00 Icebergs (54 57'S 12 76'W).
- 17/03/1996 07:40 Magnetometer, gravimeter and multibeam profiling. Italian magnetometer offset 365 m from GPS Antenna 20:52 Sound velocity profile SVP3.
- 18/03/1996 Dredge G96-01 Magnetometer, gravimeter and multibeam profiling. Dredge G96-02.
- 19/03/1996 Dredge G96-03 09:11 Magnetometer, gravimeter and multibeam profiling.
- 20/03/1996 Magnetometer, gravimeter and multibeam profiling. Very disturbed acquisition.
- 21/03/1996 Magnetometer, gravimeter and multibeam profiling. Bad weather conditions.
- 22/03/1996 Magnetometer, gravimeter and multibeam profiling. Bad weather conditions. Dredge G96-04.
- 23/03/1996 Dredge G96-05. Magnetometer, gravimeter and multibeam profiling.
- 24/03/1996 Magnetometer, gravimeter and multibeam profiling. Bad weather conditions.
- 25/03/1996 From 3.00 to 22.52 stand by meteo. Magnetometer, gravimeter and multibeam profiling. Bad weather conditions.
- 26/03/1996 Magnetometer, gravimeter and multibeam profiling. Bad weather conditions. Dredge G96-06 Dredge G96-07. Dredge lost.
- 27/03/1996 Magnetometer, gravimeter and multibeam profiling. Bad weather conditions.
- 28/03/1996 Magnetometer, gravimeter and multibeam profiling. Sound velocity profile SVP4.
- 29/03/1996 Start of Shona SMT survey. Magnetometer, gravimeter and multibeam profiling. Bad weather conditions.
- 30/03/1996 Magnetometer, gravimeter and multibeam profiling. Strong wind. Dredge G96-08. Heat Flow 01. Dredge G96-09. Sound velocity SVP5.
- 31/03/1996 Start of MAR survey. Magnetometer, gravimeter and multibeam profiling. Bad weather conditions. Heat Flow 02.
- 01/04/1996 Start of Spiess survey. Magnetometer, gravimeter and multibeam profiling. Bad weather conditions. Heat Flow 03.
- 02-03/04/1996 Magnetometer, gravimeter and multibeam profiling. Bad weather conditions.
- 04-08/04/1996 Start of Bouvet F.Z. survey. Magnetometer, gravimeter and multibeam profiling.
- 09/04/1996 Magnetometer, gravimeter and multibeam profiling. Bad weather condition.
- 10/04/1996 Magnetometer, gravimeter and multibeam profiling. Bad weather condition 17:18 Multibeam Stand by Meteo, 55 11,57'S 0 16,06'W. Italian magnetometer OK.
- 11/04/1996 18:21 End of Stand by Meteo. Magnetometer, gravimeter and multibeam profiling. Bad weather condition.
- 12/04/1996 Magnetometer, gravimeter and multibeam profiling. Dredge G96-10. Heat Flow 04.
- 13/04/1996 Magnetometer, gravimeter and multibeam profiling. Dredges G96-11, 12, 13, 14, 15, 16.
- 14/04/1996 Magnetometer, gravimeter and multibeam profiling. Dredges G96-17,18. Sound Velocity station SVP6.
- 15 -16/04/1996 Magnetometer, gravimeter and multibeam profiling.
- 17/04/1996 Magnetometer, gravimeter and multibeam profiling. Heat Flow 05. Dredges G96-19, 20, 21.
- 18/04/1996 Magnetometer, gravimeter and multibeam profiling. Dredges G96-22, 23. 17:33 Multibeam Stand by Meteo.
- 19/04/1996 Stand by Meteo, sea state 12.
- 20/04/1996 18:34 End of Stand by Meteo. Magnetometer, gravimeter and multibeam profiling. Bad weather condition.
- 21/04/1996 Magnetometer, gravimeter and multibeam profiling. Dredge G96-24.
- 22/04/1996 Magnetometer, gravimeter and multibeam profiling. Dredge G96-25, 26.
- 23/04/1996 Magnetometer, gravimeter and multibeam profiling. Big iceberg detected on radar. 05:47 End of survey (52 33,90'S 3 00'W). 08.30 Transit to Abidjan
- 24/04- 01/05/1996 Transit to Abidjan. Magnetometer and multibeam profiling.
- 04/05/1996 Bunker Port Gentil.
- 08/05/1996 Arrive in Abidjan.
- 09/05/1996 Gravimeter calibration.
- 10/05/1996 End Cruise.